Building inspections

New Home Inspections in Ontario: What Inspectors Check

A new house in Ontario gets inspected at set stages: footings, foundation before backfill, framing and rough-ins, insulation, plumbing, and occupancy, plus septic on a rural lot. The inspector checks the Building Code minimum. Quality is still on your builder.

This is for people building a custom home who want to know when the inspector shows up, what they look at, and what tends to fail.

Short answer

The Inspector Is Not Your Quality Control

I like building inspectors. A good one catches things and keeps everybody honest. But understand what they are there for. They check that the work meets the Ontario Building Code at the moments the Code says to check. They are not checking that your trim is straight or your tile is level.

An inspector may spend twenty minutes on a stage that took us two weeks. They look at what the Code requires and what is visible that day. If something is buried before they come, or happens between visits, nobody official sees it.

So the inspection is a floor, not a ceiling. The quality control is your builder’s job, every day, whether anybody is watching or not.

Bottom line: Passing inspection means the house meets the minimum. Ask your builder how they check their own work between inspections.

The stages

The Mandatory Inspection Stages for a House

The Ontario Building Code, Division C, Subsection 1.3.5, requires the builder to notify the building department when the work is ready at each prescribed stage. Your permit package will include your township’s own list. They vary a little, so read yours. Here is the typical list for a house.

Stage When to call What fails it
Footings Forms set, before concrete Footing too shallow for frost, sitting on fill or soft soil, wrong size for the drawings, rebar missing where the design calls for it.
Foundation / backfill Walls done, dampproofing on, weeping tile laid and covered in stone, before backfill Missing dampproofing or membrane, weeping tile not covered, no connection to a sump or outlet. Some departments list 6 inches of stone cover.
Underground plumbing Drains and services in, before they are covered, ready for testing Failed water or air test, wrong slope, missing cleanouts.
Framing and rough-ins Structure done, plumbing and HVAC roughed in Undersized lintels or beams, missing fire blocking, notched joists, ductwork not as designed.
Insulation and vapour/air barrier Before drywall Gaps, torn poly, unsealed penetrations, wrong insulation values for the energy design.
Fireplace or wood stove At the start of installation Clearances to combustibles, chimney height and supports.
Occupancy and final House substantially complete and safe to live in See the occupancy list below.

Book early. Some departments get to you within about two business days of a request, others are busier, and a crew standing around waiting for an inspector is money down the drain. Our page on how long a custom home takes covers what really drives the schedule, and footing depth and frost in Ontario explains the first inspection in more detail.

If you have not got the permit yet, start with our guide to building permits in Ontario.

ICF walls

ICF-Specific Checks: Rebar, Bracing, Openings Before the Pour

With ICF, the wall is the formwork. Once the concrete is in, nobody can see the steel again. That makes the moments before the pour the most important ones on the whole job.

Many building departments want to look at ICF walls before concrete, either as a separate visit or as part of the foundation inspection. Ask yours when you get the permit, and get it in writing on your inspection list. Whether they ask or not, this is what we check ourselves before a truck is ordered:

  1. Rebar size, spacing and laps match the drawings or the engineer’s design.
  2. Steel is held in place so it cannot slump during the pour.
  3. Bracing is straight, plumb and tied off every few feet along the wall.
  4. Window and door bucks are square, braced and at the right height.
  5. Sleeves for water, power, drains and dryer vents are in. Coring concrete later is no fun.
  6. Anchor bolts or ledger connections are planned for the floor that sits on top.

If the walls are taller, longer or loaded more than the prescriptive Code tables allow, an engineer designs the reinforcement and may want to inspect too. Our page on ICF engineering explains when that happens, and the ICF build timeline shows where the pour sits in the schedule.

Rural lots

Septic and Well Inspections

A septic system has its own permit under Part 8 of the Building Code. Depending on your township, the inspector may come from the building department, the health unit or a conservation authority. Expect a look at the site before or during the permit, an inspection once the system is installed and before it is covered, and paperwork showing the as-built layout.

The classic failures are simple ones. Covering the bed before the inspector sees it. Setbacks to the well, the lot line or the water that do not match the approved design. Using the wrong sand or stone. Call your township’s building department before you start and ask exactly who inspects septic on your lot. Our septic cost guide explains the system itself.

A drilled well is a little different. The well contractor is licensed by the province and files a well record. There is usually no building inspection of the well itself, but your occupancy may need proof of potable water. Public Health Ontario tests private well water for bacteria free of charge. Chemical testing, such as nitrate, goes to a private accredited lab. See well drilling in Simcoe County for the rest.

Moving in

Occupancy: What Must Be Done Before You Can Move In

The Code lets a house be occupied before every last thing is finished, but there is a list that has to be done first. Many townships issue an occupancy permit, and you cannot move in without it. Typical items include:

  • The exterior envelope substantially complete: roofing, cladding, windows, doors, insulation and air and vapour barriers.
  • Electrical service in place with an ESA final.
  • Stairs, handrails and guards installed.
  • Smoke alarms and carbon monoxide alarms working.
  • The door between an attached garage and the house in place, with the required gas-proofing and self-closer.
  • Water supply, sewage system, lighting and heating working. On a rural lot that may mean a water test and the septic sign-off.
  • Ventilation working, with the HRV balanced and a record of it.
  • Foam insulation covered with an approved finish.
  • Required plumbing fixtures installed and working.

Townships differ on what they ask for at occupancy and what can wait for the final, so get your own township’s checklist early. Moving furniture in before the occupancy permit can cost you with your lender and your insurer, never mind the township.

Worth the money

Third-Party Inspections Worth Paying For

If you want more eyes on the job than the Code requires, these are the ones I think earn their fee.

Blower door test

Measures how airtight the house is. Some energy compliance paths under SB-12 require one. Even if yours does not, a test before drywall lets you fix leaks while you can still reach them.

Pre-drywall walk-through

Walk the house with your builder before the board goes up. Photograph every wall. That photo set is worth more than you think when you hang a TV in ten years.

HVAC commissioning

Ask for the HRV balancing record and the heating system’s start-up readings. You are paying for a system that runs as designed, so check that it does.

Our page on the SB-12 energy code explains which energy paths need testing. For a look at the whole build in order, go back to the custom home building process.

Building on a rural lot this year?

Send me your drawings and the lot address. I will tell you which inspections to plan for and where the schedule usually gets held up.

Free book

How to Build a Home Without Going Broke

Not ready to call anyone yet? Fair enough. Read the book first: the costly mistakes I have watched people make over 45 years of building, and how to avoid every one of them. Free PDF, straight to your inbox.

Questions people ask

FAQ

What inspections are required for a new house in Ontario?
Typically footings, foundation before backfill, underground plumbing, framing with rough-ins, insulation and vapour barrier, any fireplace or wood stove, and occupancy and final. A rural lot adds septic. Your permit comes with your township’s list.
Who books the building inspections?
The Code puts the duty on the builder to give notice when each stage is ready. On our jobs, we book them. If you are building yourself, that job is yours.
Does an ICF wall need an inspection before the pour?
Many building departments want to see ICF walls before concrete, either as a separate visit or with the foundation inspection. Ask your township when the permit is issued. We check rebar, bracing and openings ourselves before every pour.
Can I move in before the final inspection?
Often yes, once the occupancy requirements are met and the township issues occupancy. Smoke and CO alarms, stairs and guards, heat, water, sewage and the ESA final are typical must-haves. Check your township’s checklist.
Who inspects my septic system?
It depends on the township. It may be the building department, the health unit or a conservation authority. Call your township’s building department to confirm before you start.
Is a third-party inspection worth it?
A blower door test and a pre-drywall walk-through are worth paying for. Some SB-12 energy paths require a blower door test anyway, and photos before drywall pay off for the life of the house.

Keep going

More in this topic: The Building Process

See all 12 steps of building a custom home, with every guide on the site  |  Straight answers: hours, payments, warranty, where we build

How to Build a Home Without Going Broke

Building a home in Ontario? Don't go in blind.

Get the free book How to Build a Home Without Going Broke — the costly mistakes most people make, and how to avoid them. Instant PDF to your inbox.

Real Enbridge bill: even in the coldest month, our ≈3,000 sq ft ICF show home cost just $117.45 to heat — kept at 20 °C (the month before: $99.21). See the actual bill → Unoccupied show home, heating only; your costs vary with size, finishes and use.
See a Completed ICF Home