Selections and deadlines

When Do You Have to Pick Finishes on a Custom Home?

Earlier than you think. Windows, layout and heating get decided before the permit. Plumbing fixtures and light locations get decided before the rough-ins. Cabinets get ordered long before the drywall goes up. Paint colour is about the only thing you can leave to the end.

This is for people about to build who want to know which decisions come when, why the order matters, and how to keep a late pick from turning into a delay and a change order.

Short answer

The House Gets Built in Order, So Decisions Do Too

Most people think of selections as the fun part at the end: tile, taps, light fixtures. In a real build, the deadline for each choice is set by the trade that needs the answer, not by when the item gets installed.

The plumber needs to know which shower valve you want before he roughs in, because the valve body goes in the wall months before the trim goes on. The electrician needs to know where the pendant lights hang before the drywall goes up. And with ICF, we need to know your window sizes before we pour, because after that, the opening is in concrete.

So we work backwards from the schedule. Each decision has a “need by” date, and we tell you what it is at the start, not the week before.

Bottom line: Make the big decisions before the permit, make the hidden decisions before the walls close, and order anything with a long lead time as early as you can. Late decisions cost money twice: once in delay and once in rework.

Stage 1

Before the Permit: Layout, Windows and the Heating System

The building permit is issued on a set of drawings, and those drawings carry a lot of decisions you might think of as “later” items.

  • Floor plan and room sizes. Moving a wall after permit is possible, but it can mean revised drawings and sometimes a revised permit.
  • Window and exterior door sizes, types and locations. They show up on the elevations, and their energy performance is part of your energy compliance. Our guides on SB-12 energy compliance and triple-pane windows explain why this matters.
  • Heating and cooling system. Radiant floors, a heat pump or both. The system affects the energy design, the slab and the mechanical room. The room-by-room heat loss and radiant design is done by our sister company, OntarioHeatLoss.ca.
  • Roof style, fireplace, garage and foundation type. All structural, all on the drawings.

This is the cheapest time to change your mind. A change on paper costs a designer’s hour. The same change after concrete costs a saw, a crew and a lot of patience.

Stage 2

Before the Pour and Before Framing: Openings and Structure

This is the stage that catches people who have built wood houses before. In an ICF wall, every window and door opening is formed with a buck before the concrete goes in. Once the wall is poured, that opening is set. Making it bigger or moving it later means cutting reinforced concrete. It can be done, and our page on renovating an ICF house explains how, but nobody wants to pay for it on a brand new house.

So before we pour, you confirm:

  1. Every window and door rough opening, with the actual product you are ordering, not just a size on a drawing.
  2. Penetrations through the wall: dryer vent, range hood, HRV, hose bibs, the gas line and electrical service entry.
  3. Anything big that has to go in before the framing closes up, like a one-piece tub or shower base that will not fit through a finished door.
  4. Stair type, beam locations and any structural steel.

Window lead times change with the season and the manufacturer, so get your order in as soon as sizes are locked, and ask for the delivery date in writing.

Stage 3

Before Rough-Ins: The Decisions That Hide in the Walls

Rough-in is when plumbing, wiring, ductwork and radiant tubing go in before insulation and drywall. Anything that needs a pipe, a wire or a box behind the wall has to be decided now.

Decision Why it is needed at rough-in
Shower valves and tub fillers The valve body is brand-specific and goes in the wall. A freestanding tub filler comes up through the floor at an exact spot.
Toilets, vanities and sinks Drain and supply heights change with wall-hung toilets, vessel sinks and floating vanities.
Kitchen layout and appliances Range type (gas or induction), fridge water line, dishwasher, hood size and venting route.
Light locations and switching Pot lights, pendants over the island, under-cabinet lights, exterior lights and which switch controls what.
Radiant zones and thermostats Tubing goes in the slab or subfloor early. Zones and thermostat locations follow the heating design.
Low voltage and extras Network cable, TV locations, speakers, a generator inlet, an EV charger circuit in the garage.

If you might want something later, say so now. A pipe or a wire run to an empty box during rough-in is cheap. The same run after drywall means holes and patching. A generator inlet is a good example, and our page on power outages and backup heat explains why we suggest one.

Stage 4

Before Drywall: Walk It With a Tape Measure

Before insulation and drywall, walk the house with us. Stand in each room. Look at every box, every pipe, every vent. This is your last cheap chance to move anything.

It is also when blocking goes in. Blocking is solid wood between studs so you can hang something heavy later without hunting for a stud. Ask for it behind:

  • Grab bars in every bathroom, even if you do not need them yet. Our aging in place guide explains why.
  • Wall-mounted TVs, floating shelves and heavy mirrors.
  • Upper cabinets and window coverings.

Take photos of every wall before it closes. You will use them for years.

Stage 5

Before Finishes: Cabinets, Counters, Floors and Fixtures

The finishes stage is where most of the shopping happens, but several items have to be ordered well before they are installed.

  • Cabinets. Custom cabinets are built to your drawings, so final layout and appliance specs must be locked early. Order them as soon as the layout is final. We offer them too, see custom kitchen cabinets.
  • Countertops. Stone counters are usually templated after the cabinets are installed, then cut. Pick the slab early so the template visit is not waiting on you.
  • Flooring. Over radiant heat, not every floor is a good match. Confirm the product works with radiant before you order it.
  • Tile, trim, doors and hardware. Interior doors and trim style need to be known before the finish carpenter starts.
  • Light fixtures and plumbing trim. These go on last, but they should be bought and on site before the trades come back, not ordered the week before.
  • Paint colours. The one decision you really can leave close to the end.

The money side

Allowances and What Late Decisions Cost

Many contracts carry allowances: a set amount for cabinets, flooring, lighting or plumbing fixtures. Pick something that costs more and the difference is an extra. Pick something that costs less and you should get a credit. Our page on builder quote allowances shows how to tell a realistic allowance from a lowball one.

Late decisions cost you in three ways:

  1. Delay. If the trade arrives and the answer is not there, they leave and go to another job. Getting them back can take a while.
  2. Rework. A change after the wall is closed or the concrete is poured means paying to undo good work.
  3. Rush costs. Expedited shipping, a substitute product that costs more, or a second trip for the trade.

Every change goes through a written, priced and signed change order before work starts. Our page on deposits, payments and change orders covers how those work.

Write your selections down, with model numbers. Tarion’s one-year warranty on a contract home includes protection against unauthorized substitution of items you specified or selected. That protection only works if there is a record of what you picked.

Want the selections list before you sign?

Book a call and we will walk you through what has to be decided at each stage of your build. If you have drawings, send them and we will flag the decisions hiding in them.

Selections are one step in a longer sequence. To see the whole thing from lot to keys, start with the custom home building process.

Questions people ask

FAQ

When do I have to choose windows for a custom home?
Before the permit for sizes, types and locations, because they appear on the drawings and in the energy design. On an ICF house the exact rough openings must be confirmed before the pour, since the openings are formed in concrete.
When do I need to pick plumbing fixtures?
Before the plumbing rough-in. Shower valves are brand-specific and go inside the wall, and floor-mounted tub fillers, wall-hung toilets and vessel sinks all change where pipes go. The decorative trim can come later, but the valve choice cannot.
What happens if I make a selection late?
The trade may have to leave and come back, work already done may have to be torn out, or a substitute product may cost more. Any change should go through a written, priced and signed change order before work starts.
How early should I order kitchen cabinets?
As soon as the kitchen layout and appliance specs are final. Custom cabinets are built to your drawings, and countertops are usually templated only after the cabinets are installed, so a late cabinet order pushes back the counters too.
What is an allowance in a building contract?
A set dollar amount for items you have not picked yet, such as flooring or lighting. If your choice costs more, you pay the difference as an extra. If it costs less, you should get a credit.
Should I write down my selections?
Yes, with model numbers. Tarion’s one-year warranty on a contract home includes protection against unauthorized substitution of specified or selected items, and a written record is how you show what you selected.

Free book

How to Build a Home Without Going Broke

Not ready to call anyone yet? Fair enough. Read the book first: the costly mistakes I have watched people make over 45 years of building, and how to avoid every one of them. Free PDF, straight to your inbox.

Keep going

More in this topic: The Building Process

See all 12 steps of building a custom home, with every guide on the site  |  Straight answers: hours, payments, warranty, where we build

How to Build a Home Without Going Broke

Building a home in Ontario? Don't go in blind.

Get the free book How to Build a Home Without Going Broke — the costly mistakes most people make, and how to avoid them. Instant PDF to your inbox.

Real Enbridge bill: even in the coldest month, our ≈3,000 sq ft ICF show home cost just $117.45 to heat — kept at 20 °C (the month before: $99.21). See the actual bill → Unoccupied show home, heating only; your costs vary with size, finishes and use.
See a Completed ICF Home